Lowering Mainline utilities and raising sidestreet utilities
Work Planned week of: 9/29/25
Knife River
Finish paving from Grand to Harney
Begin paving wearing course throughout 3rd Street
Raise Utilities throughout 3rd Street
TSS to install permanent signage and thermoplastic striping
Cars parked in “No Parking” zones will be towed.
Access to businesses along 3rd Street will remain open throughout the project
Parking WILL NOT be available in work zones
Watch for flagging operations, reduced speeds, traffic control and barriers
Hours of operations will be Monday-Fridays and e/o Saturday from 7am to 7pm